Summary -

In this topic, we described about the Assigning Cost Centers to Profit Center process along with technical information.

Assigning cost centers to profit center in an organization to reflect all the primary costs from Financial Accounting and all secondary allocations to profit centers in Cost Center Accounting.

Assigning a cost center to profit center, it assigns all the cost center assets to the profit center.

Step-1:- Go to SPRO.

Assigning Cost Centers to Profit Center

Step-2:- Click on SAP Reference IMG button to proceed.

Assigning Cost Centers to Profit Center

Step-3:- Navigate to SAP Customizing Implementation Guide → Controlling → Profit Center Accounting → Assignments of Account Assignment objects to Profit Center → Assign Cost Centers and click on execute to assign Cost Center to profit center.

Assigning Cost Centers to Profit Center

Step-4:- Enter the Cost Center and click on Enter.

Assigning Cost Centers to Profit Center

Step-5:- In the next screen, enter the profit center to which cost center is assigned.

Assigning Cost Centers to Profit Center

Step-6:- Click the save icon at the top to save the cost center to profit center assignment.

Assigning Cost Centers to Profit Center

Technical details: -

  • Transaction: n/a
  • Menu Path: SPRO → SAP Reference IMG → SAP Customizing Implementation Guide → Controlling → Profit Center Accounting → Assignments of Account Assignment objects to Profit Center → Assign Cost Centers