Summary -
In this topic, we described about the Assigning cost center to profit center process in detail.
Assigning cost centers to profit center in an organization to reflect all the primary costs from Financial Accounting and all secondary allocations to profit centers in Cost Center Accounting. Assigning a cost center to profit center, it assigns all the cost center assets to the profit center.
Step-1:- Go to SPRO.
![Assigning cost center to profit center](img/assign-cc-to-pc1.png)
Step-2:- Click on SAP Reference IMG button to proceed.
![Assigning cost center to profit center](img/assign-cc-to-pc2.png)
Step-3:- Navigate to Controlling → Profit Center Accounting → Assignments of Account Assignment objects to Profit Center → Assign Cost Centers and click on execute to assign Cost Center to profit center.
![Assigning cost center to profit center](img/assign-cc-to-pc3.png)
Step-4:- Enter the Cost Center and click on Enter.
![Assigning cost center to profit center](img/assign-cc-to-pc4.png)
Step-5:- In the next screen, enter the profit center to which cost center is assigned and click the save icon at the top.
![Assigning cost center to profit center](img/assign-cc-to-pc5.png)